Wednesday, 29 October 2014

meetings


Meeting of Cottesmore Neighbourhood Planning Group
 in the Sports and Social Club,
Monday 27th October 2014 at 7pm

Members attending:
Frank Chivers, Linda King, Terry King, Lisa Viney, Tony McClelland, John Meara, Jack Wood, Elaine Huq, Tim Dixon, Chris Donovan, Robert Tregay, Dawn Spence, Peter Spence, Daphne Lees

1.         Apologies for absence were received from Sophie Jamieson, Ron Dane and Sharon Baker.

2.  There were no matter arising from the previous notes.

3.  Exhibition evening Friday October 31st and discussion morning Saturday November  1st..
Friday
TD and CW have produced the presentation boards and copies were circulated. The original overview of neighbourhood planning has been reused and 8 more sheets have been written based on sections in the discussion document. These are now ready at the printers.
The display boards from the last consultation will be reused. RD will be contacted to check where they are stored. If upstairs Pat Hart now holds the key. TD and CW will put up the boards, which can stay up overnight as the village Hall has been booked for 3pm on Friday for 24 hours.
EH suggested that post-it notes would be useful for residents to add comments to the boards or on the relevant sheets on the table. Several members offered to bring some.
Name and address sheets are to be completed again and JW will provide these.
Most members of the committee volunteered to attend. .Friday and
Saturday.
Talks will start at 10.30 and will last 5 - 10 minutes each.
Environment and Character - RT
Energy - Ron Dane will be asked to speak on this section
Transport and Road safety - CD
Housing - CD first 4 sections and RT the remainder
Economy - Ron will be asked if he will do this
Community - FC

Some chairs will need to be arranged in a loose circle with others available if needed.
 EH has arranged for the WI to kindly provide refreshment again.

4. Current situation regarding housing planning applications

TK informed us that the Local Plan has now been adopted  by RCC. Under the Site Allocations and Development Plan document of the plan there is no housing requirement for Cottesmore before 2026. Rutland has 5 years plus a further 20% supply of land ready for development, conforming to national government requirements. The Cottesmore NP must conform to the local plan.

Currently there are 2 housing planning applications before the council and these will be decided on the current local plan. In any future review if Cottesmore has to have house building the areas we designate in the NP will be taken into account. So what is proposed now should not affect current applications.
TK will arrange a copy of the local plan to be provided for the group.

Developers may come to the meeting and not necessarily identify themselves.  We need to be clear that areas allocated on the Cottesmore NP are not for development now, if ever.

It was agreed that the current version of the plan was very good and that RD had done a really good job of producing it and everyone wished to express their thanks to him.

5 Next version of the plan

The next version of the plan needs to be more robust in order to stop development on public open spaces. It will need to show clearly why there are key sectors of the village that should not be developed

RT suggested the factors to be taken into account and strengthened could be
Constraints including the environment
Access - near to school and shops
Sustainable
Deliverable - no ancient remains or sites of special interest etc.

The language could be more precise in planning terms. However it should remain clear to non- planners, which may not be easy. TK said the planning officer was looking at the plan and is willing to put it into planning terms. It was noted that plan inspectors have said it does not require the precise language of other planning documents so it is for us to decide.


6 EU law
SB has provided details of the EU laws that the plan will have to comply with.
a is a sustainability appraisal that the RCC will do the bulk of the work on
b is an appropriate assessment for  any impact on European special sites.

7 Any other business
The Journal of Local Planning. is paid for by the Parish Council who wished to know if it was of value and should we continue to receive it. It was felt that the articles were useful particularly as neighbourhood plans are reaching appeals and we would like the parish council to continue to fund it .JM

10 Date of next meeting is Monday 5th January 2015 in the Sports and Social Club at 7pm
FC will book the date with the social club.



meetings


MINUTES OF THE COTTESMORE NEIGHBOURHOOD PLANNING GROUP
SOCIAL CLUB
MONDAY 6 SEPTEMBER 2014 AT 7.00PM
________________________________________________________________________________________________

PRESENT:  Jack Wood (Chair), Ron Dane (Vice-Chair), Chris Donovan (Treasurer), Peter Spence,
Dawn Spence, Frank Chivers, Tony McClelland, Chris Whitton, Tim Dixon, John Meara, Spencer James,
Lisa Viney


MINUTES
ACTION


1.     Welcome and Apologies
Jack Wood welcomed everyone to the meeting and introduced Spencer James as a new member to the committee.

Apologies received from Daphne Lees, Elaine Huq, Robert Tregay, Linda King,          Terry King, and Sophie Jamieson.  Also, Sharon Baker from RCC.

2.     Matters arising from the minutes of the meeting  on 7 July.
No matters arising.

3.     Traffic  Survey Results
Members of the Committee carried out the survey on 17 September started by FC before the last meeting.  This was done in the morning and afternoon to catch the rush hours.  It was broken down into lorries, vans, cars etc.  The percentage travelling at a speed over 30mph was greater in the evening than the morning.
It was agreed that the 30mph sign was too close to the village on the Oakham side and would be better placed where the Cottesmore sign is, then the electronic sign should be before the junction to Market Overton.  JM stated that this had already been put to RCC and he would keep on top of it.  If this plan is adopted, we would be able to apply pressure on the council.

4.     Consultation Document
The policy points in the draft document were addressed and amendments were suggested.

5.     Open House – Friday 31 October & Saturday 1 November
Nine panels will need to be produced from the consultation documents.  They should have a preamble plus the policies. 
People will have to be available on the Friday to put them up.
Copies of the consultation document will be distributed to the village before the meeting.
Friday will be informal and Saturday will have a set start time when each area will be explained by the person responsible for writing it.  The attendees will then be able to discuss them in groups at tables around the room. 

A vote of thanks was made to RD for all the work he has put in.






6.       AOB
         TD had a further suggestion about the consultation document that the energy                 information should be reduced to one paragraph.  This was agreed.

7.     Date of Next Meeting
 Monday 27 October to iron out any issues relating to the Open Event
























CD, RD, TD to amend doct before Friday
JM - final read.

CW, TD to produce panels

EH to organise distribution























Tuesday, 5 August 2014

meeting

MINUTES OF THE COTTESMORE NEIGHBOURHOOD PLANNING GROUP
VILLAGE HALL
MONDAY 7 JULY 2014 7.00PM
________________________________________________________________________________________________

PRESENT:  Jack Wood (Chair), Ron Dan (Vice-Chair), Chris Donovan (Treasurer), Peter Spence,
Dawn Spence, Frank Chivers, Tony McClelland, Elaine Huq, Robert Tregay, Chris Whitton, Linda King, Terry King, John Meara (on behalf  of the Parish Council), Lisa Viney

ALSO PRESENT:  Sharon Baker (Member of the Planning Office Team of RCC), David Hodson &
Ken Edward (Greetham Neighbourhood Planning Group)

MINUTES
ACTION


1.     Welcome and Apologies
Jack Wood welcomed everyone to the meeting and introduced Sharon Baker from Rutland County Council who is responsible for this area of work.  Also David Hodson & Ken Edward who are on the Greetham Neighbourhood Planning Group and are attending to see how we are dealing with matters.

Apologies received from Daphne Lees, Tim Dixon, Sue Vaughan, Simon Day and
Sophie Jamieson.

2.     Questionnaire Summaries
RD explained that Fred Docker is doing an edited version of the summary of all the comments made in the questionnaires and this should be ready shortly.  Over 300 were collected which represents a 66% response rate (exluding the barracks). 160 people made comments on their forms, half of which were in the environmental section and the least in the energy and economy section.  Only 8% of questionnaires delivered to the Camp were completed.

Each section was then summarised:

Housing – RD
·        67% (of 196) against 4/5 bed houses, 83% (of 216) in favour of 3 bed houses, 73% (of  226) in favour of  1 & 2 bed starter homes, 77% (of 193) against blocks of apartments, 75% (of 224) in favour of retirement apartments
So, the majority in favour of 3 bed, low cost houses with some retirement dwellings but they might not be aware that there are already 78 of the 400 houses in the village are bungalows
·        89% (of 238) supported proposition that any future building should be in keeping with the older elements of the village
·        45% (of 194) supported brick and concrete tiles
·        76% (of 227) materials should be chosen to conserve energy
·        Almost total unanimity for no building to be above 2 storeys and that the village retained its appearance and character

       Environment and Facilities – CW
·        239 of 300 responses felt that the character of the village should be retained whilst improving the kerbs, pavements and footpaths with wider paths on Main Street and pavement parking outside the chip shop


·        Nearly 50% felt that there were too many signs
·        Dog Waste signs should be reduced in size
·        Some signs restrict drivers’ view
·        Signs required for horses, and children
·        Over 75% thought a Doctor’s surgery was required
·        151 responses thought there should be allotments but only 61 would use one
·        Majority felt that any new housing should have a recreation area – particularly Harrier Close
·        Over 75% requested increase in access to the countryside
·        196 felt there should be more done for older people
·        Many suggested more integration with the barracks and use of facilities
·        General consensus that happy with facilities but many felt improvements should be made to the village shop and that other outlets should be introduced such as a coffee shop and hairdresser

       Transport - CD
·        260 responded to questions in this section out of the 300 questionnaires returned. Often, however, responses were in direct conflict which each other and perceived problems vary considerably
·        75% did not favour lowering the speed limits or widening roads. 
·        Curbs and signage should be made clearer
·        Speed control signs should be further from the edge of the village
·        Humps not favoured
·        Nearly 80% favoured changing the signing priority of the A1 North from Oakham.  Aware this would divert traffic to the A606 instead but the Cottesmore road is a B road
·        Nearly 80% seek a limit of HGVs through the village but support the industry and quarries which are sited in this area
·        Parking should be better organised for chip shop and pub.  Village Hall parking should not be used for general parking.  Parking needs to be restricted on Mill Lane where is meets Main Street and more action taken against irresponsible parking.
·        Limited support for improvements to junction of Mill Lane and Main Street as well as Ashwell Road and Market Overton Road.  Less support for a roundabout at Exton Road.
·        Some support for improved cycle tracks
·        Calls for safer route from Barrow to Cottesmore for school children and a pedestrian crossing in the centre of the Village and from Harrier Close across Rogues Lane
·        Over 80% felt the need for regular buses to Stamford and almost as many supported better frequency of buses to Oakham and Melton Mowbray

       Economy and Energy - RD
·        80% in favour of a Village Trade Directory
·        84% in favour of another Bed & Breakfast
·        50/50 for and against change of use from residential to retail




·        Mainly against industrial units.  If one, suggested Rogues Lane, Market Overton Road, near the school or near the tip
·        Out of 300 replies, 58 people were identified as self-employed.  Taken as a proportion of the total households in the Village, this would amount to 87 self-employed people in the Village. 

       Energy - RD
·        80% supported the need for more information on this subject
·        67% supported helping households change suppliers
·        61% in favour of community buying  schemes
·        Of the 250 replies in this section, 56% against the introduction of solar panels and 43% quite happy with the idea but majority thought they should not be seen from Main Street
·        Of the 258 replies in this section, 60% against the use of wind turbines and 40% in favour.  General consensus it that they should be out of sight – Barracks, Market Overton Road / Ashwell Road where windmill used to be.

      There then followed some discussion on the feedback received.
·        RT pointed out that, when considering and making recommendations for development sites, we need to be aware that there are European regulations, Government guidance and legal test cases, as well as good practice methodologies that define how we should go about the process.  We also need proposals that bear some relationship to objectively defined housing needs etc in the Local Authority- Rutland- area, although these are not yet known for the next Plan Period, so we need to focus on (i) flexible, broad proposals that fit with our Vision for the village and (ii) potentially, specific sites where we are sure we want development to proceed irrespective of Local Plan developments. Any proposals need to have a proper evidence base and need to take account of planning principles, sustainable development objectives and constraints that might apply. In short, it is a technical and expert process.  That doesn’t mean we can’t say what we want, but we can’t just ’make it up’.  Development sites need to be justified. It is also important to separate what is in our hands and what isn’t.  He also cautioned against coming up with detailed proposals at this stage in the Neighbourhood Plan process- there is a long way to go and we don’t have the evidence base yet.  
We should therefore concentrate on the VISION – what we want for our village. He suggested that, based on the first round of consultation responses, we should not put forward detailed proposals but, rather, put forward broad themes and priorities reflecting where it appears people want to go.  This can be tested at the next village consultation. 
It is a priority that we obtain the GIS base from RCC (listed buildings, flood areas etc) which will tell us what we do have to take into account.  Neighbourhood Plans are not expected to have such a high standard as those from developers and councils but we are still expected to be aware what the constraints and opportunities are.  We will then have the technical information to underpin what we want.  Sharon Baker said this was available.                                
Also, it would be helpful to have precedent boards showing examples of good practice in other villages  eg Castor & Ailsworth’s road calming scheme.  If we could use these boards at the next village consultation day, it would help to explain to villagers what is required and assist with the vision. 


·        JM stated that the Parish Council was in discussions with RCC over traffic.  Best practice examples would be helpful before that meeting.  TK said there was some evidence for speed humps and some information on traffic volumes for Greetham and Cottesmore.
·        Sharon Baker agreed to send some links to the Council’s evidence base, site location documents and economic data.

3.     Communication
RD will be putting the summary of the questionnaire on the Blog but it was agreed that the committee should have a chance to comment on it before it is uploaded.  It was also agreed that it would be a good idea to print out 100 – 200 copies of it for people to read if they wished.  Use The Link to ask if people would like one and put in the shop, pub and social club.  TK said that his office would be happy to copy them for the price of the paper only.

It was agreed that it is very important to keep getting the message out to the Village about this plan.  We should put something in The Link every month, using the logo each time.  TK explained that, when it is time to vote, a proper electoral system is adopted.  CD suggested, therefore, that that we should canvass properly on the run up to the voting date, which was agreed.

4.     Next Step
This matter was postponed until the next meeting.

5.     Rutland County Council
Sharon Baker stated that the Neighbourhood Plan has to be in accordance with the  Council’s core strategy in relation to planning.  Sites have been allocated up to 2026 but this is still awaiting the Inspector’s report.  She is confident these sites will meet the requirements but there is still a possibility that further housing could come to Cottesmore in that time.  TK explained that the strategy is reviewed every 5 years so there is always risk but other sites usually come forward.  Oakham will also be favoured over villages as it has all the services and everything is in one place.                               

RT thought that it would be most helpful to have what has just been said written down simply for the next Village consultation day.

CD stated that developers are only just waking up to the fact that Neighbourhood Plans can undermine their plans. 

JM wondered what the reaction of RCC would be if, in spite of no allocation for housing in Cottesmore, an application for more was submitted.  Sharon Baker said that, if the Neighbourhood Plan supported it, so would RCC.  If a speculative one came in, RCC would not support it as they have the allocation in place.

6.     Financial Update
CD stated that there was not much to add since the last meeting.  The £1700 required for the last consultation has been paid and we are solvent.  We must bear in mind that the rules stipulate that all the money given to us is spent by the end of 2014.
JW requested a hard copy of all the financial records which he can keep.



7.     Matters Arising
·        Sharon Baker agreed to resend the Service Agreement.  The Parish Council will sign it.
·        The Terms of Reference have been done and are on file.

8.     Any Other Business
JM mentioned the question of extending the footpath from Cottesmore to Exton.  It appears that there might be some money available to get this done.  It is likely to be in a rural finish rather than tarmac, however, so not the best surface for cycling.  The Committee should therefore be aware that some of the suggestions made could already have been implemented.

9.     Date of Next Meeting
Monday 11 August at 7pm






              











































































































































If necessary,
RT will speak to RCC about what we require













TK to make sure we obtain this



RD to distribute summary and upload to Blog



















TK will work with Sharon Baker to produce this









CD to provide JW with hard copies of financial records


Monday, 16 June 2014

Link to survey results: http://cnpg14survey.blogspot.co.uk/

meetings



Meeting of Cottesmore Neighbourhood Planning Group
held at the Village Hall, Cottesmore,
Monday 9th June 2014

1 Members attending:
Chris Donovan, Elaine Huq, Tony McClelland, Robert Tregay, Lisa Viney, Ron Dane, Peter Spence, Dawn Spence, Chris Whitton, Daphne Lees

 Apologies for absence were received from:
Frank Chivers, Tim Dixon, Sophie Jamieson, Linda King, Terry King, Jack Wood. and John Meara.

In the absence of Jack Wood, Ron Dane chaired the meeting

2 Questionnaire

Distribution and collection
600 questionnaires were distributed in both the village and Kendrew Barracks. 295 have been collected to date. Considering only the village and excluding the barracks that is a response rate of well over 50% which is a very encouraging response.

Data analysis
Approximately 250 of the straightforward yes/no answers have been inputted and a copy distributed to members. Many questionnaires contain comments and show an impressive interest in the suggestions. Points of interest were that 50 people are self employed which seems quite high and that 54 people would be interested in having an allotment. Better access to the countryside by the provision of more footpaths was also very well supported.

Packs of completed questionnaires containing comments were distributed to all the members attending the meeting for collating question answers.
Using a word document and a separate page headed with the area, e.g. housing, economy etc, note the question number and list the comments made for each. Type in full if short but if a long comment abbreviate and note that they have been abbreviated. Scan the maps if possible or send to Ron to do.

Action: All members at meeting. These to be completed by 20th June it to allow Ron to distribute the comments for summarizing.

Ron will distribute the listed comments for summarising by
Rob Lees, (deputy to Daphne Lees) - Housing
Environment and Facilities - Chris Whitton
Transport - Chris Donovan
Economy and Energy - Ron Dane
The summaries are to be completed before the next CNPG meeting.

The summaries can then be put together in one document.

3 Communication

The summary will be published in the village link.
Action: Lisa Viney

The results will be put on the CNPG blog as soon as available.
Action: Ron Dane

The results of the survey will be used in the autumn as the basis for consultative discussions with residents regarding the different areas.

They will form part of the Data Book of evidence for the Neighbourhood Plan submission documents

4 Where next?

It was felt that we really are at the stage where input is needed from Rutland County Council, who have not attended any of our meetings, despite invitations.
We need to know what the council is considering for the future development of Cottesmore. As one of the full service villages in Rutland it is almost certain there will be some residential development but whether it is 20 homes in the next 10 years or 200 makes a difference to our decisions about acceptable locations. We also need information about future transport policies, schools and we should be provided with better planning maps to facilitate discussions.

Decision: when the data is available after the next meeting a letter will be dispatched to the Director of Planning requesting a meeting and the provision of the  
 Essential information.

5  Financial position - Chris Donovan

Income                                         1000                                           
from Parish Council
 from Government                         5400*

Total                                                                £6400

Expenses
3/02/14       Hire of village hall    6.50
12/0214       Travel                     10.00
12/02/14      Display boards       74.00
21/05/14     Village Hall hire       59.00        
                 ( 16&17/05 & 9/06 )
Total                                                                  £149.05

Printing
800 village postcards                      230.40
600 questionnaires                          510.00
7 display panels and artwork           300.00
80 consultation events prints            45.00
50 village plan questionnaires         126.00

Total                                                                     £1211.40
* £600 still to come from government, paid in 2015.


6 Matters arising from the previous meeting on 28th April 2014 not on the agenda

The proposed roundabout at the junction of Mill Lane and the Main Road was raised at the Parish Council meeting.

Action: Tony McClelland will check whether any decision has been made about this.

7 Any other business

The service level agreement between CNPG and the Parish Council appears not to have been finalised.
Action: Tony McClelland to discuss with Jack Wood and John Meara


8 Date of next meeting
The next meeting will be on Monday 14th July at 7pm in the Upper Room of the Village Hall. Lisa Viney agreed to write the meeting notes in the absence of Daphne Lees.

Daphne Lees

Secretary CNPG